Success Story – Bank Nizwa TB and Trade Project

Future Proof Solution

Comprehensive RFP – 2100++ Requirements across Functional and Technical

18 Vendors Evaluated

All RFP Requirements signed-off by all relevant stakeholders

Evaluation Model appreciated by Gartner and ITSC

Business Process Improvements – SOP reviews and Gaps

Compliance Requirements (Additional)

Reduced Implementation Risk

Each Requirement mapped with the Evaluation Model

Proposal Defense Workshops – Active selection of POC vendors

Functional deep dive with 3 Vendors – Product capabilities, roadmap, vendor commitments

Stakeholder Mapping –All relevant departments involved/interacted from initial stages

Avoiding post contract Commercial Implications – Unearthing Vendor Proposal Gaps

Working Together

Encouraging Bank Stakeholder’s active participation in Evaluation Process

Evaluation Phase Project Management by TXN team

Delays mitigated with planning, adapting & Quick responses

  • 1 Week delay due to Information Sharing Protocols
  • 2 Weeks in releasing the RFP owing to Stakeholder discussions and Approval
  • 1 Week extension given to Vendors on request from all vendors
  • 10 Days Delay in opening the RFP by Tender Committee – Corona Impact
  • Eid Al-Adha Holidays
  • Cost Optimizations / Negotiations
Lorem ipsum dolor sit amet, consectetur adipisicing elit. Optio, neque qui velit. Magni dolorum quidem ipsam eligendi, totam, facilis laudantium cum accusamus ullam voluptatibus commodi numquam, error, est. Ea, consequatur.
Lorem ipsum dolor sit amet, consectetur adipisicing elit. Optio, neque qui velit. Magni dolorum quidem ipsam eligendi, totam, facilis laudantium cum accusamus ullam voluptatibus commodi numquam, error, est. Ea, consequatur.
Lorem ipsum dolor sit amet, consectetur adipisicing elit. Optio, neque qui velit. Magni dolorum quidem ipsam eligendi, totam, facilis laudantium cum accusamus ullam voluptatibus commodi numquam, error, est. Ea, consequatur.